7/31/2025  -  Site update 

7-31-2025   Site update.   Building D masonry work is almost complete.   All permits approved and miving forward on Building B

Building D - Masonry Work 

07-03-2026   Video of the masonry work being completed on Building D

Building D - Pad Pour

6-16-2025 -   Building D pad is poured.    Building D will have 6 units plus the bathrooms.

Building D - Forms are ready  for Slab

6-7-2025 Building D forms are ready for our FIRST slab pour.

Stormwater Drains

4-24-2025 Stormwater drains and pipes are being installed at the job site.   Not much longer until we start BUILDING!

Construction Level

4-11-2025   The construction site is now up to level to start building.  Next step is the underground storm sewer piping.  

Drone Footage - Update Site Development

2-21-2025 .....   Drone footage of the progress with site development.   

Site Cleared

11-20-2024......  site is cleared.

WATCH US GROW.........

Welcome to Premier Storage Condos.   We are so excited to show you our project.   We will be posting photos as the project progresses.   Follow along and watch us grow.....

©Copyright. All rights reserved.

We need your consent to load the translations

We use a third-party service to translate the website content that may collect data about your activity. Please review the details in the privacy policy and accept the service to view the translations.